A Coordination Unit, runs the project. It is composed by two representatives from each partner. It is chaired by the Lead Partner. As. Prof.Nikolas Zouros is the project manager.
Project management is based on the sub-division of the various tasks into four components. The Project Manager is responsible for the management and coordination of all project activities and for the timely achievement of the project deliverables. He has the leading role in team-building, and is the channel of communication with the INTERREG Technical Secretariat.
The Lead partner is responsible for all the administrative and financial management of the project.
All invoices are being submitted to the Lead Partner in order to be controlled and paid. Financial management is provided through the establishment of a project specific, suspense account through which all payments and receipts are processed. An indepent auditor is autiding the financial reports from the partners and the combined total progress report of the project.
Coordination Unit
Lead Partner: Natural History Museum of the Lesvos Petrified Forest - Lesvos island - Greece
Representatives : Zouros Nickolas, Valiakos Ilias
Partner No2: Reserve Geologique de Haute Provence - France
Representatives : Martini Guy, Giraud Sylvie
Partner No3: GAL ISC Madonie - Sicily - Italy
Representatives : Tilotta Nino, Modica Rosaria
Partner No4: Geological Survey of Ireland - Republic of Ireland
Representatives : John Morris, Cowman Des
Partner No5: Provincia Regionale di Enna - Sicily - Italy
Representatives : Troia Salvatore, Amato Giuseppe Maria
Partner No6: Naturepark Nördlicher Teutoburger Wald Wiehengebirge - Germany
Representatives : Escher Hartmut, Kluttig Timo
Partner No7: LAG Gesäuse-Eisenwurzen - Austria
Representatives : Heinz Kollmann, Reinhart Mitterbäck
Partner No8: Development Agency of mountainous area of Milopotamos and Malevizi S.A. – Crete - Greece
Representatives : Pattakos Dimitrios, Fassoulas Charalambos
Partner No9: Fermanagh District Council - Northern Ireland - UK
Representatives : Watson Richard, McKeever Patrick
FINAL CONTRACT:
Signing of final contract on the 19/12/2003 by Dr Nickolas Zouros and Mme María BONILLA Musoles
START UP REPORT:
With the start up report the Lead partner informs the Joint Technical Secretariat (JTS) about setting up the management structures within the operation, especially with regard to the Coordinator, Financial Manager and Auditor of the operation and the composition of the Steering Group.
PROGRESS REPORTS:
The progress report covering the period June 2003-April 2004 was submitted in September 2004
A combined progress report covering the period June 2003-October 2004 was submitted in December 2004
The progress report covering the period November 2004-May 2005 was submitted in August 2005
COORDINATION MEETINGS:
Several coordination meetings were held.
INTERREG III C LEAD PARTNER SEMINARS:
The project manager participated in 3 lead partners seminars were the operation and management of the project has been discussed
1st Seminar - July 2003 Valencia Spain
2nd Seminar - December 2004 - Rotterdam
3rd seminar - May 2005 - Valencia Spain
INTERREG III C FORUM
In December 2004 the INTERREG III C Forum was organized by the INTERREG III C Authorities in Rotterdam. The European geoparks Network was presented and its result were discussed durring a thematic workshop.